"Even if you're on the right track, you'll get run over if you just sit there." -Will Rogers

This page contains links to SkiffAmerica's Building Log Pages. 
I received the plans from Kilburn Adams in November 2001. As with most projects, it takes longer than you planned to get the project really started. I studied the plans off and on for the next four months and I started ordering wood, epoxy,  and hardware in April 2002. 

The launching  was January 2004. Just a word about the time I took to finish my SkiffAmerica, I really had to stop working on the boat starting in July. Except for a few hours each week. I was too busy working out of town and taking vacations in September. I have now worked about 825 hours on the boat as of January 2005. Like all boat owners I will always enjoy working on something.

I have added some of my answers  to questions I have been ask that may be of interest to other builder in the Notes page.